A Partnership Dedicated to Keeping the Community Informed on All Aspects of the Napa Railroad Relocation Project





This three year-plus project consists of these major construction phases

3300 linear feet of new railroad track

·         Track raised between two and five feet in elevation

·         New higher track approximately 35 feet east of existing track

·         Track raised from South Soscol Avenue crossing to Napa Street

           -   May 9th through July 1st 2011

           -   January 9th through January 27th 2012



 
Aerial view of track to be raised

North Soscol Avenue rail crossing

·            Three feet higher in elevation

·         Partial lane closures, no complete street closure, one lane maintained in each direction

          -   February 1st through February 26th 2010

          -   April 14th through May 4th 2010

          -   June 1st through November 8th 2010

·         Reconstruction of streets, sidewalks, ramps and driveways

         -   June 15th through July 3rd 2011

         -   July 5th through August 10th 2011

        -    January 9th through January 27th 2012


North Soscol rail crossing



Realign South Soscol Rail Crossing

      ·         New rail placed at adjacent alignment

      ·         Intermittent lane closures throughout the project duration

      ·         One lane in each direction maintained during lane closures

      ·         Lane closure schedule:

                -   August 24th through September 16th 2010

                -   December 27th through December 30th 2010

                -   February 25th through March 3rd 2011

                                  COMPLETE

South Soscol rail crossing



Raise First Street rail crossing

·         Five feet higher in elevation

·         Partial lane closures (road open to EB traffic only)

          -   March 1st through March 12th 2010

·         Complete street closure between Soscol Avenue and McKinstry Street

          -   March 15th through June 16st 2010

          -   July 11th through August 5th 2011


First Street at ribbon cutting - March 2010           ·         Reconstruction of streets, sidewalks, ramps and driveways

                                                                       ·         Construct retaining walls, relocate utilities

                                                                       ·         Construct new storm drain facilities, street lighting, landscaping and irrigation

 

Raise Third Street rail crossing

·         Three feet higher in elevation

·         Partial lane closures (Road open to EB traffic only)

          -   April 25th through May 6th 2011

·         Complete street closure between Soscol Avenue and Burnell Street

          -   August 16th through December 15th 2010

          -   June 13th through July 8th 2011

·         Lawrence Street will become northbound only permanently

·         Reconstruction of streets, sidewalks, ramps and driveways



Third Street as of January 2011


Build new Oxbow bypass railroad bridge

·         Parallels Soscol Avenue and McKinstry St.

·         Between Napa Valley Wine Train station and First Street

·         First half complete - May 2011

·         Bypass portion complete - May 2012




Status as of March 2011


Build new railroad bridge over the Napa River


·            North of first Street

·         Four feet higher in elevation

·         35 feet to the east of the existing bridge

·         Eliminates the railroad bridge as a flood obstruction

·         Two houses demolished for new track alignment

·         Complete - June 2011




Current and new rail bridge