3300 linear feet of new railroad track
· Track raised between two and five feet in elevation
· New higher track approximately 35 feet east of existing track
· Track raised from South Soscol Avenue crossing to Napa Street
- May 9th through July 1st 2011
- January 9th through January 27th 2012
Aerial view of track to be raised
North Soscol Avenue rail crossing 
· Three feet higher in elevation
· Partial lane closures, no complete street closure, one lane maintained in each direction
- February 1st through February 26th 2010
- April 14th through May 4th 2010
- June 1st through November 8th 2010
· Reconstruction of streets, sidewalks, ramps and driveways
- June 15th through July 3rd 2011
- July 5th through August 10th 2011
- January 9th through January 27th 2012
North Soscol rail crossing
Realign South Soscol Rail Crossing 
· New rail placed at adjacent alignment
· Intermittent lane closures throughout the project duration
· One lane in each direction maintained during lane closures
· Lane closure schedule:
- August 24th through September 16th 2010
- December 27th through December 30th 2010
- February 25th through March 3rd 2011
COMPLETE
South Soscol rail crossing
Raise First Street rail crossing
· Five feet higher in elevation
· Partial lane closures (road open to EB traffic only)
- March 1st through March 12th 2010
· Complete street closure between Soscol Avenue and McKinstry Street
- March 15th through June 16st 2010
- July 11th through August 5th 2011
First Street at ribbon cutting - March 2010 · Reconstruction of streets, sidewalks, ramps and driveways
· Construct retaining walls, relocate utilities
· Construct new storm drain facilities, street lighting, landscaping and irrigation
Raise Third Street rail crossing
· Three feet higher in elevation
· Partial lane closures (Road open to EB traffic only)
- April 25th through May 6th 2011
· Complete street closure between Soscol Avenue and Burnell Street
- August 16th through December 15th 2010
- June 13th through July 8th 2011
· Lawrence Street will become northbound only permanently
· Reconstruction of streets, sidewalks, ramps and driveways
Third Street as of January 2011
Build new Oxbow bypass railroad bridge
· Parallels Soscol Avenue and McKinstry St.
· Between Napa Valley Wine Train station and First Street
· First half complete - May 2011
· Bypass portion complete - May 2012
Status as of March 2011
Build new railroad bridge over the Napa River
· North of first Street
· Four feet higher in elevation
· 35 feet to the east of the existing bridge
· Eliminates the railroad bridge as a flood obstruction
· Two houses demolished for new track alignment
· Complete - June 2011
Current and new rail bridge